Pittsfield to Host Webinar for the Pontoosuc Lake Park Project

Print Story | Email Story
PITTSFIELD, Mass. — The City of Pittsfield Department of Community Development is hosting a Zoom webinar on Thursday, January 25 at 7:00 p.m. to discuss planned improvements to Pontoosuc Lake Park.
 
The city was recently awarded a Massachusetts Parkland Acquisitions and Renovations for Communities (PARC) grant to begin the plan implementation. Attendees at this virtual meeting will hear about what is being considered as part of the master plan that was developed in 2021.
 
Advance registration for this webinar is required. Information on how to register can be found here and at www.cityofpittsfield.org under Parks and Recreation. For more information, please call Jim McGrath at (413) 499-9344.

Tags: Pontoosuc,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Pittsfield Council OKs $3M Borrowing for Failing PHS Boilers

By Brittany PolitoiBerkshires Staff

PITTSFIELD, Mass. — The City Council has authorized the borrowing of $3 million for new boilers at Pittsfield High School — a project that was originally going to be funded by ARPA.

The nearly 100-year-old boilers are original to the building and have exceeded their useful life, officials say. They are converted locomotive engines that are extremely inefficient and expensive to maintain.

The replacement design was recently completed and a low bid was received. After looking at the numbers, it was clear that the allocated $1 million in American Rescue Plan Act funds would not be enough.

"$213,210 was spent on emergency repairs and the design work for the replacement project," Finance Director Matthew Kerwood confirmed in an email.
 
"The low and only bid for the replacement was $2,482,000, however given the complexity of this project I felt that a 20 percent contingency would be needed which gets to the $3,000,000 authorization. If the entire amount is not needed, the remaining unused balance will be rescinded at some point in the future."

The project is also time-sensitive, as one boiler is non-operational and another is severely compromised. If they fail during the heating season, the school will have to close.

"The contractor that was the low bid, in 30 days he can walk away from that bid if he wants to, and the other problem is I need to get this project underway to hopefully get them in and running by the time school reopens up for wintertime," Building Maintenance Director Brian Filiault explained.

"This is a major project, a major project. We're taking three locomotives out of that building and it's no easy thing. I mean, the building is built around it and we have a small portal that we actually will be able to get it out, we'll have to crane everything else. It's a very labor-intensive, very hard job, and I'm afraid of the timeframe because I can't run those boilers again. They've gone as far as they're going to go."