STOCKBRIDGE, Mass. The Massachusetts Department of Transportation (MassDOT) announced crews will be conducting daytime and overnight hour guardrail repair, drainage work, bridge repair, tree trimming, and deck pour operations at various locations and times on I-90 eastbound and westbound during the week of Monday, April 8.

Lane closures will be in place during the construction operations and traffic will be able to travel through the work zones.  The schedule for the work and lane closures will be as follows: 

Otis/Blandford

  • Guardrail repair operations will be conducted nightly on I-90 westbound between mile marker 21.0 and mile marker 27.0 from Monday, April 8, through Friday, April 12, from 7:00 p.m. to 5:30 a.m. the next morning. The work is expected to conclude by 5:30 a.m. on Friday, April 12. 
  • Drainage work will be conducted on I-90 eastbound between mile marker 21.0 to 23.0 on Monday, April 8, from 7:00 p.m. to 5:30 a.m. the next morning.

Blandford

  • Bridge repair work will be conducted nightly on I-90 eastbound and westbound at mile marker 26.1 from Monday, April 8 through Friday, April 12, from 7:00 p.m. to 5:30 a.m. the next morning. The work is expected to conclude by 5:30 a.m. on Friday, April 12

Russell

  • Tree trimming work will be conducted on I-90 westbound between mile marker 33.0 to mile marker 36.0, from Monday, April 8 through Friday, April 12, from 7:00 a.m. to 3:30 p.m. each day. 

Stockbridge

  • Deck pour operations will be conducted on I-90 westbound at mile marker 7.6 on Monday, April 8, from 7:00 a.m. to 3:30 p.m. 

Appropriate signage, law enforcement details, and messaging will be in place to guide drivers through the work area. 

Drivers traveling through the affected areas should expect delays, reduce speed, and use caution.  

All scheduled work is weather dependent and subject to change without notice. 

For more information on traffic conditions, travelers are encouraged to:  

  • Download the Mass511 mobile app or visit www.mass511.com to view live cameras, travel times, real-time traffic conditions, and project information before setting out on the road. Users can subscribe to receive text and email alerts for traffic conditions. 
  • Dial 511 and select a route to hear real-time conditions.?   
  • Follow @MassDOT on X, (formerly known as Twitter), to receive regular updates on road and traffic conditions.  

Tags: MassDOT,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

South County Road Maintenance

LEE, Mass. — The Massachusetts Department of Transportation (MassDOT) is announcing crews will be conducting daytime and overnight hour guardrail repair, drainage work, bridge repair, and tree trimming operations at various locations and times on I-90 eastbound and westbound during the week of Monday, May 20.

Lane closures will be in place during the construction operations and traffic will be able to travel through the work zones.  The schedule for the work and lane closures will be as follows: 

Otis/Blandford 

  • Guardrail and drainage work will be conducted on I-90 westbound between mile marker 22.0 to 26.6 from Monday, May 20, through Thursday, May 23, from 7:00 p.m. to 5:30 a.m. the next morning. The work is expected to conclude by 5:00 a.m. on Friday, May 24.

Otis

  • Bridge repair operations will be conducted nightly on I-90 eastbound and westbound at mile marker 22.5, from Monday, May 20, through Thursday, May 23, from 7:00 p.m. to 5:30 a.m. the next morning. The work is expected to conclude by 5:00 a.m. on Friday, May 24.

Blandford

  • Bridge repair operations will be conducted nightly on I-90 eastbound and westbound at mile marker 26.4 from Monday, May 20, through Thursday, May 23, from 7:00 p.m. to 5:30 a.m. the next morning. The work is expected to conclude by 5:00 a.m. on Friday, May 24.

Russell

  • Tree trimming work will be conducted daily on I-90 westbound between mile marker 30.0 to mile marker 31.0, from Monday, May 20, through Thursday, May 23, from 7:00 a.m. to 3:30 p.m. each day. 

Stockbridge/West Stockbridge

  • Guardrail and bridge repair work will be conducted nightly on I-90 eastbound and westbound from mile marker 3.0 to 6.0, from Monday, May 20, through Thursday, May 23, from 7:00 p.m. to 5:30 a.m. the next morning. The work is expected to conclude by 5:00 a.m. on Friday, May 24.

Stockbridge

  • Bridge repair operations will be conducted daily on I-90 eastbound and westbound at mile marker 7.5, from Monday, May 20, through Thursday, May 23, from 7:00 a.m. to 3:30 p.m. each day.

West Stockbridge

  • Bridge repair operations will be conducted daily on I-90 eastbound and westbound at mile marker 0.6, from Monday, May 20, through Thursday, May 23, from 7:00 a.m. to 3:30 p.m. each day.

Lee

  • Drainage work will be conducted nightly on I-90 eastbound and westbound from mile marker 8.0 to 14.0, on Monday, May 20, through Thursday, May 23, from 7:00 p.m. to 5:30 a.m. the next morning. The work is expected to conclude by 5:00 a.m. on Friday, May 24.

Appropriate signage, law enforcement details, and messaging will be in place to guide drivers through the work area. 

Drivers traveling through the affected areas should expect delays, reduce speed, and use caution.  

All scheduled work is weather dependent and subject to change without notice. 